SUMMARY OF INTERIM REPORT JANUARY-MARCH 2016
Adaptation of the operations at Pampalo to the prevailing gold price is ongoingThe full interim report, in Swedish only, is available on the Company´s website, www.endomines.com Highlights Q1/2016 (vs Q1/2015) · Gold production was 58.5 kg (131.3) in accordance with the introduction of Selective Mining in 2016 · Milled ore tonnage was 35,317 tonnes (76,089) · Revenues were 16.3 MSEK (31.7) · Profit after tax was -14.8 MSEK (-32.6) · Earnings per share amounted to -0.02 SEK (-0.05) · The rights issue announced late 2015 was successfully completed bringing 66.6 MSEK,