A new eco-friendly housing development in London is getting the energy for its heating and hot water directly from the Thames in a pioneering community heating scheme that could be replicated in many of our major towns and cities.

Edward Davey, the Secretary of State for Energy and Climate Change, today paid a special visit to the site to switch on the heat pump-based heating system in an official launch of the innovative, renewable system.

The £70 million mixed-use development has been created by NHP Leisure Developments on the site of a former power station right in the heart of Kingston upon Thames, and 200 metres from the banks of the river. 

The development includes 56 homes called Kingston Heights for national affordable housing provider Affinity Sutton, plus 81 luxury private apartments known as River Walk provided by Redrow London.  The 137 apartments, built by specialist contractor and developer, United House, will all benefit from the cutting-edge heat pump system that harvests naturally stored energy from the River Thames.

The community heating scheme takes renewable heat from the sun, stored in the river water and boosts it to the temperature required for the underfloor heating and hot water needed by residents: “At two metres below the surface the water never falls below 7°C, even in winter, so we can be certain that it can provide enough energy to heat the apartments,” explains Mike Spenser-Morris, managing director of NHP Leisure Developments and the visionary behind the scheme. 

“If we had fitted gas boilers, then the site would be dumping around 500 additional tonnes of carbon into the atmosphere each year. In addition, because of this system’s exceptional energy efficiency, the equivalent heating cost for a couple living in a one bedroom apartment would be 18% more. For an average home, this would mean hundreds of pounds extra.”

The system can draw up to 13 million litres of water each day – the equivalent of five Olympic-sized swimming pools.  The river water passes through a state-of-the-art, two-stage filtration process that ensures no marine life can enter the system.

Inside a specially-built plant room adjacent to the river, the water passes through high-efficiency heat exchangers and, once the low grade heat has been harvested, the water is immediately fed back into the river, untreated in any way. 

The heat exchangers transfer this low grade heat from the river water to an internal ‘closed’ loop water system and this is then carried 200 metres to a plant room in the apartment building, where Mitsubishi Electric’s advanced heat pump technology boosts the low grade heat to the temperature required for the apartments’ heating and hot water.

Towards the end of 2014, the construction of a new 142-bedroom hotel, with meeting, banqueting and conference facilities, will also be completed at the site, which will increase the efficiency of the heating scheme further still.

The Doubletree by Hilton hotel will derive all its heating and hot water, as well as its cooling, from the open water heat pump installation.  Heat recovered from cooling the individual hotel rooms will be reclaimed and returned to the community system to support the heating and hot water demand for the whole site.

Mike Spenser-Morris believes the scheme paves the way for other developments taking place near an open body of water, to benefit from this highly energy efficient system, doing away with the need for traditional combustion boilers, with their attendant carbon emissions.

“This open water heat pump system will be capable of producing over two megawatts of thermal energy for this development and will provide it 24/7, 365 days a year regardless of the weather or air temperature, even in the depths of winter,” he explains. “Almost every major city in this country is close to a river, lake, reservoir, canal or the sea.

“Every litre of water naturally stores, with the greatest efficiency, the valuable energy the sun delivers to earth each day,” adds Spenser-Morris.  “There will be thousands of homes and businesses that can benefit from this most energy-efficient technology and in the process prevent thousands, even millions of tons of harmful carbon being released into the atmosphere from now on”.  

Edward Davey, Secretary of State for Energy and Climate Change and MP for Kingston and Surbiton, will be switching on the development’s innovative heating system, harnessing the power of the Thames. He said:

“Kingston Heights is a great example of how sustainable solutions can help power entire communities. I want to see a community energy revolution where projects like this are the norm, not the exception.

“This project will not only transform the waterfront area in Kingston, but also means residents’ bills will be lower than if they used gas.

“The Thames is a great natural asset to Kingston and London as a whole. By capturing the heat permanently stored in the river to provide heat and hot water to the whole development the project shows the enormous potential of renewable energy.”

Ends

Picture caption, left to right: Donald Daw, Commercial Director, Mitsubishi Electric; Mike Spenser-Morris, NHP Leisure Developments – the visionary behind the scheme; Jeffrey Adams, Chief Executive of United House; Edward Davey, MP, Secretary of State for the Department of Energy and Climate Change.  Inside the development where heat from the river is upgraded and sent to the apartments. 

Kingston Heights / River walk – the facts and figures:

  • The community heating system uses Ecodan heat pump technology from Mitsubishi Electric to upgrade sensible heat from the Thames and deliver consistent heating and hot water to the apartments.
  • The system will generate approximately 2.3 MW of heat output.
  • An average of 75 litres per second will be abstracted from, and returned to, the Thames when each of the filtration units is on.  This could equate to 13 million litres per day and is the equivalent of five Olympic-sized swimming pools per day.
  • The Thames flow rate is 260,000 litres per second so the maximum that the system would abstract is 0.05% of the available water in the river.
  • The change in temperature of the abstracted water is at most only 3 degrees – a difference that would be assimilated almost immediately.
  • A two-stage system of state-of-the-art filtration has been installed to ensure that no fish fry or other marine life can enter the system.
  • Mike Spenser-Morris appointed White Associates as his Sustainable Energy consultants for the system development.
  • Specialist contractor and developer United House Ltd was contracted to build and manage the project.
  • The construction project included the technically challenging encapsulation of a live UK Power Networks substation within a steel-lined concrete ‘box’ 200 metres long, 38 metres wide and four storeys high.
  • Christopher Smith Associates were appointed by NHP Leisure Developments as quantity surveyors and project managers for the project.
  • Paul Brookes Architects were the architects responsible for the design of Kingston Heights and KDS Associates were appointed as project delivery architects.

Note to editor:

Founded in 1921, Mitsubishi Electric is a global, market leading, environmental technologies manufacturer, producing an advanced range of heating, air conditioning and ventilation equipment. The company realises that ensuring the right solutions are selected for each individual building, requires collaboration by all involved. Mitsubishi Electric has therefore changed the way it does business to ensure engagement with all involved in delivering sustainable buildings so that together, we can make a world of difference.

The NHP Group was founded by Mike Spenser-Morris and three partners in 1991. The group has been responsible for many major regeneration projects in London, as well as luxury residential developments, affordable housing schemes, student housing projects, retail park and leisure developments.

United House is a leading housing specialist offering innovative solutions across London and the south as a developer, contractor and investor. The company, founded in 1964, has achieved impressive, consistent growth, with a turnover of £197 million for 2012, reflecting its outstanding track record for delivering an unrivalled combination of social housing new build, refurbishment, regeneration, mixed use, Public Private Partnerships and private residential schemes, investing in the communities where it works. The company is a pioneer of low-carbon retrofit to reduce fuel poverty. United House Developments won Housebuilder of the Year at the What House? Awards 2011 and Homebuilder of the Year at The Sunday Times British Homes Awards 2012, for its exemplary and design-led approach to high-end development in prime locations. www.unitedhouse.net

For further editorial information please contact:

Russell Jones, PR & Communications Manager: Email: russell.jones@meuk.mee.com or telephone: 01707 278772

MEL/048/13

Media

Media

Quotes

“Kingston Heights is a great example of how sustainable solutions can help power entire communities. I want to see a community energy revolution where projects like this are the norm, not the exception.
Edward Davey, MP, Secretary of State for Energy and Climate Change