Teollisuuden Voima Oyj Interim Report January-June 2020
During the first half of 2020, Teollisuuden Voima’s (TVO) electricity generation at Olkiluoto 1 and Olkiluoto 2 plant units continued safely and reliably.The annual outages at the Olkiluoto NPP were carried out with special arrangements in place in order to prevent coronavirus infections on the power plant site. The maintenance outage implemented at the OL1 plant unit was adjusted in scope and duration from the original plan due to the exceptional circumstances. OL2 plant unit underwent a refuelling outage. TVO has received interim information of the rebaseline schedule for the