Power production March 2013 – 51.2 GWh

Report this content

The winds were normal in March. Totally 51.2 GWh were produced included the company´s share in Jädraås wind farm (19.7 GWh). The production in March last year was 35.2 GWh.

In the first quarter of 2013 126.3 GWh were produced compared to 84.3 GWh the same period last year.

Halmstad, 5 April 2013

ARISE WINDPOWER AB (publ)                                                        

The information contained herein constitutes information which Arise Windpower AB is legally required to publish under the Swedish Securities Market Act (2007:528) and/or the Swedish Financial Instruments Trading Act (1991:980). The information was released for publication at 13.30 p.m. on 5 April 2013.

For further information, please contact
Peter Nygren, CEO Arise Windpower AB, +46 706 300 680

About Arise Windpower
Arise Windpower is one of Sweden’s leading companies in onshore wind power. Its business concept is to sell electricity generated at the company’s own wind turbines. The company’s target is to have 1,000 MW of onshore wind power constructed and under management by 2017, of which 500 MW will remain in the ownership of the company. Arise Windpower is listed on NASDAQ OMX Stockholm.

Arise Windpower AB (publ), Box 808, SE-301 18 Halmstad, Sweden, tel. +46 (0)35 20 20 900, org.no. 556274-6726

E-mail: info@arisewindpower.se, www.arisewindpower.se