Annual outage 2018 to begin at Fortum’s Loviisa nuclear power plant

Report this content

The annual refuelling and maintenance outage of Fortum’s nuclear power plant Unit 2 in Loviisa, Finland, begins on Sunday, 5 August, followed by the servicing of Unit 1. Unit 2 will undergo the extensive inspection outage that takes place every eight years and Unit 1 the short refuelling outage. The entire outage procedure is estimated to be completed in about 64 days.

In addition to the normal periodic maintenance tasks and refuelling, several safety improvements will be implemented and completed during the annual outages, including the automation modernisation to improve the plant’s critical safety functions, ensuring the safety functions of the secondary circuit, and renewal of the emergency generators’ cooling water piping. Along with the maintenance work on the main generators, the stators of two generators will be replaced. In addition to the normal preventive maintenance work, the turbine work includes modernisation of the high-pressure turbine and inspections. During the outage, one quarter of the fuel will be replaced.

In addition to the plant modification and improvement work, Loviisa 2 will undergo the extensive inspection outage implemented every eight years, in which e.g. the pressure vessel and its inner parts will be inspected, and pressure tests of the primary and secondary circuit’s pressure equipment and pipelines will be performed.

“The annual outages and the biggest investments in the plant’s history are being implemented as part of our lifetime management programme to ensure the reliable electricity production of both plant units also in the future,” says Thomas Buddas, Deputy Manager, from the Loviisa power plant.

“The principle of continuous improvement has been our way of operating at the Loviisa power plant already for decades. The high expertise of our personnel and the high-quality team work are emphasised when challenging projects are carried out in collaboration with partners and external workers,” he continues.  

In addition to the power plant’s 500 employees, about one thousand external workers from about one hundred companies will take part in the annual outage and the ongoing projects. About 80 percent of the workers are Finns. Additionally, workers will come from Croatia, Russia, Germany, Poland and France.

Fortum Corporation
Group Communications

Additional information:
Thomas Buddas, Deputy Manager, Loviisa power plant, tel. +358 10 455 3710
Timo Eurasto, Manager, Operations unit, Loviisa power plant, tel. +358 10 455 4010

Loviisa power plant
In 2017, the load factor at Fortum’s fully-owned Loviisa nuclear power plant was 92.9%. On an international scale, the load factor was among the best in the world for pressurised water reactor power plants. The plant produced a total of 8.16 terawatt hours, which is more than 10% of Finland’s total electricity production. The Loviisa power plant employs more than 500 Fortum employees and some 100 permanent contractors. In 2017, Fortum invested about EUR 90 million into the Loviisa nuclear power plant.

Fortum
Fortum is a leading clean-energy company that provides its customers with electricity, heating and cooling as well as smart solutions to improve resource efficiency. We want to engage our customers and society to join the change for a cleaner world. We employ some 9,000 professionals in the Nordic and Baltic countries, Russia, Poland and India. In 2017, our sales were EUR 4.5 billion and 61% of our electricity generation was CO2 free. Fortum's share is listed on Nasdaq Helsinki. www.fortum.com