Fortum’s Loviisa nuclear power plant annual outage 2024 completed
FORTUM CORPORATION PRESS RELEASE 10.10.2024 Both units at Fortum’s Loviisa nuclear power plant are back in production after completion of their annual outages. Unit 2 had a short annual outage that lasted 23 days and ended on 27 August. The extensive four-year outage of Unit 1 lasted 39 days and ended on 9 October. The annual outage of Unit 2 was delayed by 2.5 days. The reason for the delay was the repair work of the fault detected during periodic inspections on the secondary circuit and the additional time required for valve testing. The annual outage of Unit 1 was initially