Healthy Win For ISG At The New Victoria Hospital

Report this content

ISG has been awarded a £2.3 million project to refurbish 25 private patient rooms and create a replacement MRI facility at The New Victoria Hospital in Kingston upon Thames.

The fast-track project involves a wide-ranging programme of strip out, refurbishment and construction activities in a busy, fully operational hospital environment. The en-suite room refurbishments will be carried out across seven individual phases, to mitigate any potential disruption to staff and patients during the upgrade. Work to create the replacement MRI facility will be carried out concurrently, with the scheme scheduled for completion by the end of the year.

The refurbishment programme involves a comprehensive strip out of the patient rooms, and the creation of enlarged high specification en-suite bathroom facilities, with new decorative finishes and floor coverings throughout, and upgraded mechanical and electrical services. The phased project has been designed to ensure that only a maximum of four rooms will be unavailable at any one time during the refurbishment scheme.

To enable the relocation and construction of the MRI facility within the hospital, ISG will install a pre-fabricated extension outside the outpatient reception area, which will house two consulting rooms and a treatment room. ISG will construct a new concrete raft foundation to accommodate the facility, which is being constructed off-site, and install all essential services, providing the hospital with a full turn-key delivery solution. ISG’s remit also includes strengthening works to the new MRI facility.

ISG’s Stuart Deverill, managing director - London, commented: “Working in any live hospital environment is challenging, with robust measures required to minimise the impact of construction activity. At the The New Victoria Hospital, private patients also expect hotel standard accommodation, which demands a high quality finish as well as considerate working patterns. Our sector expertise means that we can not only tackle these challenges sensitively but also offer the client a complete solution, including specialist commissioning services, all within the very strict deadlines required to meet commercial and patient care needs.”

Nick Hann; Tel: 07970 275251; Email: nick.hann@isgplc.com

ISG Plc is an international construction services company delivering fit out, construction and a range of specialist services, with 31 offices worldwide. The company works with owners, developers and occupiers in the public and private sector for an extensive range of industries.  ISG Plc was established in 1989 and has been quoted on AIM since 1998. Today the company has a turnover of around £1.2 billion.

For further information about ISG please visit our website www.isgplc.com