Rejlers creates conditions for carbon negative electricity production at Vantaa Energy
Vantaa Energy has chosen Rejlers as its EPCM supplier in connection with the construction of a new large-scale electric boiler at the Martinlaakso power plant in Vantaa, Finland. The project is an important milestone in Vantaa Energy’s efforts to become carbon negative by 2030 and strengthens Rejlers' position as a leading supplier of EPCM (engineering, procurement, construction management) projects.
Vantaa Energy’s goal is to produce carbon-negative energy by 2030. In the project at the power plant in Martinlaakso, a large-scale electric boiler of 60 MW and a district heating battery of 700 MWh are now being built.
“At Vantaa, we are building a hybrid system, that sometimes runs with electricity, sometimes with other production methods – always as smart and efficiently as possible. The system relies on the use of emission free methods of energy production and on the storage of energy. Electric production of heating is an important part of our goal to be a carbon-negative energy company in 2030,” says Kalle Patomeri, Business Director, Energy and Circular Economy at Vantaa Energy.
The electric boiler adapts its operation to the need for district heating and the price of electricity, which means that production can be optimized. The energy is stored in a district heating battery and released when the demand for district heating increases. This enables the storage of renewable energy from sources such as wind and solar, contributing to more sustainable energy production.
Rejlers is a catalyst for customers in the energy transition by offering technical expertise and project management throughout the project lifecycle, from pre-planning to implementation.
“Vantaa Energy’s electric boiler project is a full-scale EPCM project, where our project management professionals are responsible for, among other things, project management, procurement, detail engineering, construction management, site supervision and commissioning. This is our first major project delivery to Vantaa Energy and, at the same time, a significant step for us towards an even stronger position as a supplier of industrial EPCM projects,” says Jussi Likitalo, responsible for industrial project deliveries at Rejlers.
Beginning in June 2024, the project is expected to be completed by autumn 2025.
Image: (c) Mari Waegelein/Vantaa Energy
For further information, please contact:
Mikko Vaahersalo, CEO, Rejlers Finland, + 358 44 425 3143, mikko.vaahersalo@rejlers.fi
Malin Sparf Rydberg, Director of Communications, Rejlers Group, +46 70 477 17 00, malin.rydberg@rejlers.se
About Rejlers
Rejlers is one of the leading engineering consultancy firms in the Nordic region. With cutting-edge expertise, we help companies, public authorities and other organisations meet tomorrow's societal challenges. Our services are important building blocks for achieving a sustainable society. Founded in 1942, Rejlers success is built on the ability to constantly embrace new knowledge. Our vision "Home of the learning minds" guides us to continuous learning, development and growth. With operations in Sweden, Finland, Norway and the United Arab Emirates, Rejlers has 3200 experts in technology areas such as energy, industry, infrastructure and real estate. In 2023, the company had a turnover of 4.1 billion SEK and its class B share is listed on Mid Cap, Nasdaq Stockholm. www.rejlers.com