Rottneros Packaging has started manufacturing in new premises
Rottneros Packaging moved into new, suitable premises in 2018 and started manufacturing moulded fibre trays in early 2019. The total investment in the new factory amounts to approximately SEK 45 million and mainly consists of a tailor-made system for preparing pulp and four machines for the manufacture of trays. The latest machine was purchased at the end of March and is put into operation by the end of 2019. After commissioning and trimming, the capacity in the factory will amount to 50-80 million trays per year, depending on the size of trays produced. The trays are primarily