The Olkiluoto 2 plant unit is back in production
The Olkiluoto 2 power plant unit (OL2)was synchronized back to the national electricity grid on Monday, September 4th, at 8:06 PM.
A leakage was detected in the water-cooled generator of the Teollisuuden Voima Olkiluoto 2 nuclear power plant unit on Friday, August 18th, leading to the suspension of electricity production at the plant. The production outage lasted for 17 days.
The faulty rotor has now been replaced, and the electricity production of OL2 was able to resume today. The power ramp-up will take approximately 50 hours.
Real-time production capacities of the Olkiluoto nuclear power plant units can be monitored at www.tvo.fi.
For further information, please contact:
Johanna Aho, Head of Communications, tel. +358 40 729 0822
Teollisuuden Voima Oyj on tuottanut sähköä omistajilleen, suomalaisille teollisuus- ja energiayhtiöille, turvallisesti ja luotettavasti jo yli 40 vuotta. TVO:n Olkiluodossa tuottaman ydinsähkön osuus on Olkiluoto 3:n säännöllisen sähköntuotannon alettua noin 30 prosenttia Suomen sähkön tarpeesta. Ilmastoystävällinen ydinsähkö palvelee yhteiskuntaa ja vähentää energiantuotannon ympäristökuormitusta. Olkiluotoon on rakenteilla myös maailman ensimmäinen käytetyn ydinpolttoaineen loppusijoituslaitos.