The regular electricity production of OL3 EPR will be postponed due to extension of turbine overhaul
Teollisuuden Voima Oyj (TVO) has received additional information from the plant supplier Areva-Siemens consortium that the regular electricity production of the OL3 EPR plant unit will be further postponed for three months due to extended turbine overhaul and inspection works.
During the turbine inspection works, the plant supplier has decided to extend the overhaul to all three low-pressure turbines in order to perform further inspections on them.
According to the received information from the plant supplier, the start-up of the OL3 EPR reactor, i.e. first criticality, will take place in January 2022, first electricity production will take place in February 2022, and the regular electricity production in June 2022.
OL3 plant supplier consortium is constructing the plant unit under a fixed-price turnkey contract. The supplier consortium companies, AREVA GmbH, AREVA NP SAS and Siemens AG, have joint and several liability for the contractual obligations until the end of the guarantee period of the plant unit.
Further information:
Jouni Silvennoinen, OL3 Project Director
Interview requests:
Elina Heikkilä, Team Leader, Communications, tel. +358 44 231 4484
Teollisuuden Voima Oyj has produced electricity for its shareholders, Finnish industrial and energy companies, safely and reliably for over 40 years. Nuclear electricity generated at TVO's Olkiluoto plant covers approximately one sixth, increasing to nearly one third once Olkiluoto 3 EPR is completed, of the electricity consumption in Finland. Climate-friendly nuclear electricity not only benefits society but also reduces the environmental impact of energy production. Moreover, the world's first final disposal facility for spent nuclear fuel is under construction in Olkiluoto.