The start of OL3 EPR’s regular electricity production postponed to September

Report this content

According to information received from the plant supplier, the regular electricity production of the OL3 EPR plant unit starts in September 2022, instead of the previously estimated start at the end of July.

Inspection and repair needs concerning the cooling system of OL3’s generator will last approximately three weeks. The plant unit’s test production programme and electricity production will continue after the repair work. Furthermore, additional time has been reserved in the schedule for the plant unit’s upcoming testing and their analyses based on previous experiences from the test production phase. 

The inspection and possible repair needs of the generator’s cooling system are not related to the information given earlier this week about the boron pumps turning on unexpectedly and related automation modifications. 

The production forecast for the test production phase can be followed online at www.tvo.fi/ol3forecast. An urgent market message will be released in Nordpool on any significant changes.

The OL3 EPR plant supplier consortium is constructing the plant unit under a fixed-price turnkey contract. The supplier consortium companies, AREVA GmbH, AREVA NP SAS, and Siemens AG, have joint and several liability for the contractual obligations until the end of the guarantee period of the plant unit.

For further information and interview requests, please contact:
Johanna Aho, Head of Communications, Tel. +358 (0)40 729 0822

 

Teollisuuden Voima Oyj has produced electricity for its shareholders, Finnish industrial and energy companies, safely and reliably for over 40 years. Nuclear electricity generated at TVO's Olkiluoto plant covers approximately 30 percent of Finland’s electricity demand once Olkiluoto 3’s regular electricity production has started. Climate-friendly nuclear electricity not only benefits society but also reduces the environmental impact of energy production. Moreover, the world's first final disposal facility for spent nuclear fuel is under construction in Olkiluoto.