Everfuel – Q2 2024: Focus on HySynergy 1 completion and execution of realigned strategy
Herning, Denmark, 28 August 2024 – Everfuel A/S today published its second quarter 2024 financial results. Key events Q2 2024: · HySynergy 1 commissioning progressing according to revised plan towards start-up later in the second half of 2024 · Submitted proposal for project Frigg, an up to 2 GW H2 production facility, uniquely positioned for the coming Danish-German pipeline · Opening of first hydrogen bus depot in Germany · Seven trailers in operation serving bus station and bus depot · Additional legacy assets sold in Q2 · Q2 EBITDA of EUR -2.7 million (EUR -4.4