NYAB and Energiequelle sign BoP contract for Mikonkeidas wind farm
NYAB has signed a Balance of Plant (BoP) contract regarding the new Mikonkeidas wind farm constructed in Kristiinankaupunki, Ostrobothnia. The value of the contract is nearly EUR 18 million. Construction work will begin in February, and work for power plant installations will be completed in early 2024. The entire project is scheduled to be completed in September 2024.NYAB shall supply the wind farm’s roads, lifting areas, foundations, internal grid, substation and transmission line construction to Energiequelle. In practice, this means that NYAB is responsible for everything in the