Project status update: First phase of offshore installation Dragon 12 completed in Vestmanna, Faroe Islands
Minesto, leading ocean energy developer, has today successfully completed the first phase of Dragon 12 (1.2 MW) offshore installation in Vestmanna, Faroe Islands. The 3.4 km main subsea cable was laid on the seabed, from the onshore grid connection point to the offshore installation node.After transit across the North Atlantic Ocean to Vestmanna, the cable installation work was commenced and was successfully completed today. The cable installation was completed in a 22-hour operation. “This cable is the highest valuable component of the infrastructure, and it’s a major milestone to have