The start of OL3 EPR’s regular electricity production postponed to September
According to information received from the plant supplier, the regular electricity production of the OL3 EPR plant unit starts in September 2022, instead of the previously estimated start at the end of July.Inspection and repair needs concerning the cooling system of OL3’s generator will last approximately three weeks. The plant unit’s test production programme and electricity production will continue after the repair work. Furthermore, additional time has been reserved in the schedule for the plant unit’s upcoming testing and their analyses based on previous experiences from the test