The construction of Jokeri Light Rail to begin in early June
Press release April 30, 2019 at 8:00 amThe Espoo City Council approved the new cost estimate for Jokeri Light Rail on Monday, April 29. The delivery of the light railway will be based on alliance contracting. The cost estimate drawn up during the development stage puts the cost for the railway infrastructure at 386 million euros, calculated at the price level in November 2018. The alliance will also deliver the depot and, possibly, other related projects. The City of Helsinki will contribute 268 million euros and the City of Espoo 118 million euros of the total estimate. The Helsinki City