Teollisuuden Voima Oyj Interim Report January–September 2021
During the first three quarters of 2021, Teollisuuden Voima’s (TVO) electricity generation at the Olkiluoto 1 (OL1) and Olkiluoto 2 (OL2) plant units continued safely and reliably.The fuel loading of the Olkiluoto 3 EPR plant unit (OL3 EPR) was completed in April 2021. Due to extended turbine overhaul and inspection works, the plant unit will be connected to the national grid in February 2022, and regular electricity production starts in June 2022 according to the updated schedule received from the plant supplier Areva−Siemens consortium in August 2021. The agreements regarding the