Everfuel: HySynergy update
Herning, Denmark, 24 April 2024 - Everfuel A/S today provides an update on the commissioning of the 20 MW HySynergy 1 electrolyser. The Company continues to progress commissioning focused on the sub-systems required to start production and delivery of green hydrogen. As previously communicated, the main electrolyser facility is ready for start-up, while some sub-systems experience delays following commissioning tests. This is impacting the planned start-up of the HySynergy 1 facility with production now expected to commence in the second half of 2024. Testing, verification and