Plant supplier updates the schedule of OL3-project
The plant supplier Areva-Siemens Consortium will perform a schedule review and provide Teollisuuden Voima Oyj (TVO) by an overall rebaseline schedule for the final phases of the project in June.The modification outage work during the first quarter of the year at Olkiluoto 3 has not been progressing according to the updated schedule issued by the plant supplier Areva-Siemens Consortium in November 2018. Based on the information provided by the plant supplier the fuel will not be loaded to the reactor before the end of August. According to the plant supplier’s schedule, nuclear fuel was