GROUNDWORK CONTINUES AND CONSTRUCTIONPLANNING HAS BEGUN
Sotkamo Silver has since autumn 2016 prepared the Silver Mine for production by building a new access road to the site for heavy traffic and other roads to the mine area, totally two kilometres have been added. Necessary ground works to remove top-soil from the ground have been done and irregularities in the ground have been levelled. Construction of an access road to the tailings storage facility has begun and preparation for production of the existing production tunnel proceed per plan. In addition, Sotkamo Silver has signed an agreement concerning foundation planning of the plant