Release of Q3 2018 interim report postponed as court ruling for dispute related to Södertörn facility received
As earlier communicated the Group has had a dispute with one of the Södertörn facility’s main suppliers. The Group has withheld the final payment due under the construction contract, as it has deemed that the counterparty failed to perform its duties under the contract. The counterparty has demanded that payment be made including some additional works. The disputed payment has been under arbitral review. The Group has denied any obligation to pay the demanded amounts and has filed a counterclaim for fees and expenses incurred to rectify faulty deliveries, which exceeds the amount of the