Interim Management Statement 1 January-30 September 2023
CEO Dr Martin Edlund:” Minesto has a unique competitiveness in the global energy transition”Significant events July-September 2023 In September, the manufacturing of the Dragon 12 wing is completed and the system integration is initiated at quayside in Uddevalla port, Sweden. The quayside completion of the kite enables an efficient shipment directly to Minesto’s tidal energy production site in Vestmannasund, Faroe Islands. Also, the build and functional testing of sea-bed connection system for the Dragon 12 was completed during the quarter. By that, the unique connection system,