Tyra II: Successful Lift of Process Module
Oslo, 4 October 2022: Norwegian Energy Company ASA ("Noreco" or the "Company") is pleased to announce the successful offshore lift and of the Tyra II process module (the "TEG") at 08:27 local time this morning. The 17,000 metric tons process module was safely lifted onto the waiting jackets and installed by Heerema Marine Contractors’ Sleipnir – the world’s largest crane vessel. Following the successful lift, all eight platforms are now in their final position, and Tyra II is several steps closer to producing valuable natural gas for decades. Over the coming weeks, Sleipnir will lift