Low-emission steel piloted for the first time in Fingrid's substation structures in Harjavalta
Enersense International PlcPress release, 6 June 2024 at 2:00 p.m.Enersense, a provider of zero-emission energy solutions, won a contract in Fingrid's public bidding process at the beginning of the year for the construction of three new 110 kV substations in the Harjavalta area. The substations will be built as gas insulated switchgear (GIS) using a gas insulation solution that does not contain any SF6 gas which is a significant greenhouse gas. As part of the project, Enersense's delivery includes all steel structures to be built in the substation area, requiring a total of 76,000 kg