Interim Report January – June 2017
Significant events during the second quarter 2017 · A Letter of Intent was signed with Rail Cargo, a subsidiary of Austrian state owned ÖBB, regarding future logistics between the mine and harbour. · Consultants were contracted and work commenced with the mine planning and production scheduling for the feasibility study. As part of that work the geotechnical data generation was completed and the report is expected in August. The data and models generated from the geotechnical and hydrogeological data have been used to set the parameters for the mine (stope) design and the mine