Teollisuuden Voima Oyj’s Interim Report 1 January–30 September 2024
During the first three quarters of 2024, Teollisuuden Voima’s (TVO) electricity generationat the Olkiluoto 1 (OL1), Olkiluoto 2 (OL2) and Olkiluoto 3 (OL3) plant units continued safely. The total electricity production of the plant units during the period in review was 16,822 (17,622) GWh.Electricity production at OL2 was suspended on 9 September 2024 due to an increase in humidity observed at the turbine plant’s generator. The plant unit reconnected to the grid on 6 October 2024 following the replacement of the failed rotor. Electricity production at OL2 will initially continue at a lower