Successful launch of first Dragon Class tidal powerplant
Minesto, leading marine energy developer, has now successfully completed the first week of commissioning including satisfactory electricity production and verification of all core functionality with the new Dragon 4 tidal power plant in Vestmanna, Faroe Islands. The kite has generated first electricity to grid right "out of the box" and the commissioning plan has been executed as planned.“We are very pleased to announce that the first week of commissioning of Dragon 4 has been successfully completed. Every aspect of the project has been fulfilled according to plan and electricity has been