Keliber Upgraded the Process and Supplemented the EIA Report of the Kokkola Plant
The process of Keliber’s lithium chemical plant in Kokkola has been developed since the assessment report of the environmental impact assessment (EIA) procedure was completed on 6 March 2020. The company has now supplemented the EIA report to reflect the current project plan. The process changes apply to the treatment of effluent and analcime sand, which is a by-product created in the process. A supplemented EIA report was submitted to the ELY Centre of Southern Ostrobothnia on 31 March 2021. ELY will issue a supplemented reasoned conclusion on the report.According to the original plan,