Pampalo mine deepening and decline development started as planned and progressed very well in April
Endomines AB, Stock Exchange Release 28 April 2021 at 12:00 CEST Endomines reports that the re-start of operations at Pampalo mine is continuing to progress very well and all work phases of the re-start are moving forward according to plans and on schedule. Refurbishment of the existing decline was completed as planned in mid-April, including re-construction of the decline road, work on mine dewatering improvements and power network upgrades. The underground mine infrastructure proved to be in good operating order after the two-years care and maintenance period, and this has enabled