Minesto's tidal power plant in grid-connected operation - commercial performance verified
Leading marine energy developer Minesto has according to plan successfully commissioned the first unit of tidal power plant “Dragon 4” in grid-connected operation in Vestmannasund, Faroe Islands. The company announces today that the commissioning results verify commercial performance and are fully in line with simulation results.The first tidal power plant from Minesto's product line Dragon Class, Dragon 4 (100 kW), has been commissioned in Vestmannasund, Faroe Islands, in early summer. The first phase of electricity generation shows that predicted performance is achieved in line with