Annual outages completed in Olkiluoto
The annual outages have been concluded in Olkiluoto for this year. They ended yesterday, Friday, May 19th at 2:00 PM, when the Olkiluoto 2 power unit (OL2) was connected to the national grid. However, due to a turbine fault, the plant had to disconnect soon after connecting and was able to resume electricity production today, Saturday, May 20th at 3:59 PM. The refuelling outage at the Olkiluoto 1 plant unit (OL1) was completed already on 26 April. The total duration of the annual outages at both the OL1 and OL2 plant units was about four weeks.The outage at OL2 started on 1 May and took 17