Keliber Progress Report April-June 2022
Keliber has today, 22 July 2022, published the Progress Report of the Lithium Project in April-June 2022. During the spring and early summer, Keliber managed to achieve several of its goals. Q2 in Brief: · No recordable injuries. “Safety first” meetings in cooperation with contractors began. · Funding for the Keliber Project secured - Sibanye-Stillwater to become the majority owner. · The lithium chemical plant was granted the environmental permit, including the right to start operations despite possible appeals. The building permit was granted in April. · Zoning of Keliber’s