Valhall Flank West successfully installed
The Valhall Flank West topsides were installed on the Valhall field on Saturday 22 June. This is just 14 months after the first steel was cut at Kværner’s yard in Verdal. Both the topsides and the jacket were delivered ahead of schedule, under budget and with no serious injuries.Aker BP is the operator of the Valhall Flank Vest with Pandion as partner. The platform is the first to be delivered under the wellhead platform alliance between Aker BP, Aker Solutions, Kværner and ABB. It sailed from Kværner in Verdal on Sunday 16 June and arrived at the field with no carry-over-work from the yard.