Fortum’s Loviisa nuclear power plant annual outage 2022 completed
FORTUM CORPORATION BUSINESS PRESS RELEASE 17.10.2022 Both units at Fortum’s Loviisa nuclear power plant are back in production after completion of their annual outages. Unit 2 underwent an extensive annual outage, which is done every 4 years; the outage lasted just over 36 days and was completed on 12.9.2022. The short annual outage of Unit 1 lasted 29 days and was completed on 16.10.2022. The annual outage of Unit 2 was delayed by approximately five days from the original plan. The delay was caused by the replacement of a main reactor coolant pump, which had failed during the start-