BlueNord: Update on Tyra Redevelopment Project
Oslo, 29 April 2024: Reference is made to stock exchange notice published on 18 April 2024 by BlueNord ASA (“BlueNord” or the “Company”) related to the operational occurrence with the IP compressor temporarily impacting the commissioning of the new Tyra facilities during the ramp-up and testing period. Continued efforts and investigations are ongoing, however, the export volumes from Tyra II are expected to be impacted for the month of May 2024. Currently, the duration of the testing program and commissioning plan for achieving the technical milestones and driving the ramp-up to 8,1