Teollisuuden Voima Oyj’s Interim Report 1 January–30 June 2023
During the first half of 2023, Teollisuuden Voima Oyj’s (TVO) electricity generation at the Olkiluoto 1 (OL1) and Olkiluoto 2 (OL2) plant units continued safely and reliably. The test production programme for the Olkiluoto 3 EPR plant unit (OL3) was completed, and regular electricity production started on 16 April 2023.TVO confirmed the provisional takeover of the OL3 plant unit for the warranty period which started on 18 April 2023; commercial operation started on 1 May 2023. OL3 significantly improves Finland’s self-sufficiency in terms of electricity and helps in achieving the goals for