Endomines’ processing plant at Friday reaches mechanical completion
Commissioning pending tailings area repairsEndomines AB, stock exchange release 26 April 2019 at 08:45 CEST Endomines’ processing plant for the Friday mine in Idaho, USA, has reached mechanical completion of all major installations including the crushers, conveyors, ball mill and flotation cells. The equipment has been successfully test-run without load. Some minor installation tasks still remain relating to the bypass line to the tailings pond and certain other plumbing work. Since early March, the spring run-off and freezing and thawing conditions have caused challenges, including wet