Start-up of Metsä Group’s bioproduct mill to begin in August 2017
Metsä Group made the decision concerning the largest investment in the history of Finnish forest industry in April 2015, and the large-scale project at Äänekoski has progressed as planned – on schedule and according to the budget – towards the mill’s start-up. At the moment, the bioproduct mill project is in the departments’ trial run and commissioning phase.Metsä Group made the decision concerning the largest investment in the history of Finnish forest industry in April 2015, and the large-scale project at Äänekoski has progressed as planned – on schedule and according to the budget –