The fuel loading of the OL3 plant unit started
The fuel loading of the Olkiluoto 3 EPR plant unit, which is to last approximately a week, started today on Saturday, March 27, 2021.During the months following the fuel loading, maintenance and finalization work will be continued, and tests will be performed. The most important test is the hot functional test, in which the reactor and turbine island is tested for use. During testing, dozens of separate tests are performed with different pressure and temperature levels. The previous hot functional test was completed in 2018. As communicated previously, the electricity production of OL3