BlueNord: Update on Tyra Redevelopment Project
Oslo, 8 July 2024: Reference is made to stock exchange notice published on 6 May 2024 by BlueNord ASA (“BlueNord” or the “Company”) related to the need for repair of the transformer for the IP gas compressor impacting the timing of the ramp-up to maximum technical capacity. The hook-up and commissioning work on the Tyra West and Tyra satellite fields are successfully concluded, however a technical issue has occurred with the Low Pressure (LP) compressor transformer. The operator, TotalEnergies, confirms that immediate actions have been taken to remedy the impact and initiate repairs and all