BlueNord: Update on Tyra Redevelopment Project
Oslo, 6 May 2024: Reference is made to stock exchange notices published on 18 April 2024 and on 29 April 2024 by BlueNord ASA ("BlueNord" or the "Company") related to the operational occurrence with the IP compressor (“Intermediate Pressure (IP) gas compressor”) temporarily impacting the commissioning of the new Tyra (“Tyra II”) facilities during the ramp-up and testing period. The investigation now confirms that the technical issue relates to the transformer delivering power to the Intermediate Pressure (IP) gas compressor. The operator, TotalEnergies, has concluded that the