Scandinavian ChemoTech push forward previously communicated target of 15 commercial installations in India to Q1-2024
ChemoTech expects to sign three new commercial contracts in Q4-2023, in addition to the three already communicated, thereby pushing the previous stated target of 15 commercial contracts in India during Q4-2023 to Q1-2024.The reason for postponing the goal of 15 commercial installations in India to Q1-2024 is linked to delays in negotiations as a result of the recent cyclone “Michaung” in the Chennai area. “The discussions and contract signings are taking somewhat longer due to this external event, but is by no means affected in terms of how they are progressing. We have not lost one