The regular electricity production of OL3 EPR will be postponed due to extension of turbine overhaul
Teollisuuden Voima Oyj (TVO) has received additional information from the plant supplier Areva-Siemens consortium that the regular electricity production of the OL3 EPR plant unit will be further postponed for three months due to extended turbine overhaul and inspection works.During the turbine inspection works, the plant supplier has decided to extend the overhaul to all three low-pressure turbines in order to perform further inspections on them. According to the received information from the plant supplier, the start-up of the OL3 EPR reactor, i.e. first criticality, will take place