Successful delivery and installation of new Tyra jackets
Oslo, 28 September 2020: Norwegian Energy Company ASA («Noreco» or “the Company”) is pleased to announce the successful installation of two new jackets at Tyra. The milestone moves the Tyra Redevelopment project into a new phase. The next milestones are for the new modules currently being fabricated to be delivered from the yards and transported to the Danish Continental Shelf for installation. Taking first delivery from the yardsToday, the two jackets were confirmed safely installed on Tyra according to plan after completing fabrication in the yard, Dragados Offshore S.A, in Spain.