Metso Outotec to deliver rotary kiln system for Lynas Kalgoorlie’s greenfield project in Western Australia
Metso Outotec Corporation’s press release on July 15, 2020, at 10:00 a.m. EESTMetso Minerals has signed a contract with Lynas Kalgoorlie Pty Ltd for the supply of a large rotary kiln and combustion system for baking rare earth elements. The order value of approximately EUR 13 million has been booked in Metso Minerals’ Q2 2020 orders received. Commissioning of the kiln is expected to take place in 2022. Commenting on the award, Lynas CEO and Managing Director Amanda Lacaze said: “The kiln is the longest lead time item for our Kalgoorlie project and placing this order is an important